as usual I was reading 1 of my favorite columns and DEAR PAO has a NEW article

 regarding what rights (at least on paper) that 1 has regarding CONDOS and not yet completed or still Unfinished.

 Hope the article can be of use to those who are Considering purchasing a New Condo on installment

 

 

Dear PAO,
I purchased a condominium unit on instalment basis from a real estate developer.

They said that the project would be finished by the beginning of the year, and I would be able to move in to my unit. However, the real estate company failed to complete the project on time.

Worse, the project seems like it cannot be finished any time soon. What are my remedies under the situation?

Mary Jane

Dear Mary Jane,
A condominium owner or developer is obliged to comply with the contractual obligations that arise from agreements it executed, as well as the legal obligations that the laws impose upon it

. In case of failure to comply, the injured party, often the buyer, is entitled to the protection and remedies provided by the laws.

 

Pertinent to the matter at hand is Section 20 of Presidential Decree No. 957,

 

otherwise known as the Subdivision and Condominium Buyer’s Protective Decree, which essentially states that a buyer has two (2) remedies in case the condominium owner or developer fails to complete the project according to the approved plans and within the specified time limit, to wit:

 

(1) the buyer may suspend amortization payment until such time that the condominium owner or developer complies with his obligation;

 

or (2) the buyer may demand reimbursement of the total amount he or she paid with legal interest less interest paid on account of delinquency. The option to choose which remedy to avail is given to the buyer who is the aggrieved party in the situation.

 

Should the buyer choose the option to suspend amortization payment, the buyer is required by law to merely notify the condominium owner or developer of the decision to suspend payment on account of the latter’s failure to comply with its obligation to complete the project to enforce such right.

The law does not prescribe any form of notice to make the right effective. Hence, it need not be in written form. A verbal notice would suffice (Zamora Realty and Development Corporation vs. Office of the President, 506 SCRA 591).

 

Moreover, the law does not require the buyer to secure a clearance from the Housing Land Use and Regulatory Board (HLURB) before exercising such right (Francel Realty Corporation v. Sycip, 469 SCRA 424). Thus, the buyer may exercise the right to suspend payment without any need of going to court or quasi-judicial body.

 

On the other hand, should the buyer opt to avail of the remedy to demand reimbursement of the total amount paid, he or she may do so by demanding refund from the condominium owner or developer.

If the latter unjustifiably refuses or unreasonably delays in giving reimbursement, the buyer may file a complaint before the HLURB which has jurisdiction to hear and decide claims involving refund and any other claims filed by subdivision lot or condominium unit buyer against the project owner, developer, dealer, broker or salesman (PBCom vs. Pridisons Realty Corporation, 688 SCRA 200).

 

http://www.manilatimes.net/condo-unit-buyer-can-stop-paying-instalments-unfinished-project/140249/

 

  • Like 1
Link to comment
Share on other sites

Gator
Posted
Posted

Good info, thanks!

 

Should the buyer choose the option to suspend amortization payment, the buyer is required by law to merely notify the condominium owner or developer of the decision to suspend payment on account of the latter’s failure to comply with its obligation to complete the project to enforce such right. The law does not prescribe any form of notice to make the right effective. Hence, it need not be in written form. A verbal notice would suffice

 

Even though verbal notice may be legal, I think it would still be best to have an attorney draw up a letter of intent, have it notarized and then send it to the developer via a courier service where you will get written proof of delivery too.

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...